ATTENTION Please.....!!
Solve it as fast as you can......!!
A can complete a work in 10 days, B in 12 days and C in 15 days. All of them began the work together, but A had to leave the work after 2 days of the start and B, 3 days before the completion of the work. How long did the work last?
Answers
Answer:
7 days
Step-by-step explanation:
Method - 1 :
A can complete the work in 10 days.
Work done by A in 1 day = (1/10)
B can complete the work in 12 days.
Work done by B in 1 day = (1/12).
C can complete the work in 15 days.
Work done by C in 1 day = 1/15.
Amount of work done by them in 1 day,
=> (1/10) + (1/12) + (1/15)
=> 15/60
=> 1/4
Let the work last for 'x' days.
Given, A had to leave the work after 2 days of the start and B, 3 days before the completion of the work.
A's 2 day work + B's(x - 3) day work + C's x day work = 1
=> 2 * (1/10) + (1/12) * (x - 3) + (1/15) * x = 1
=> (1/5) + (x - 3)/12 + (x/15) = 1
=> (x - 3)/12 + x/15 = 4/5
=> 5(x - 3) + 4x = 48
=> 5x - 15 + 4x = 48
=> 9x = 63
=> x = 7
∴ Work will last for 7 days.
------------------------------------------
Method - 2:
Work done by A in 1 - day = 1/10.
Work done by B in 1 - day = 1/12
Work done by C in 1 - day = 1/15
Here,
Initially 3 of them work together for 2 days. One of them leaves after working for 'x' days and at last C remains work for 3 days.
So,
2(1/10 + 1/12 + 1/15) + x(1/12 + 1/15) + 3(1/15) = 1
=> (2/10 + 2/12 + 2/15) + x(1/12 + 1/15) + (3/5) = 1
=> x(1/12 + 1/15) = 3/10
=> x(3/20) = 3/10
=> x = 2
Hence,
So, the total number of days required to complete the whole job as per the constraints set in the question = 2 + 3 + 2 = 7 days.
∴ Work will last for 7 days.
Hope it helps!
Wishing you a happy and safe Holi dear !!! :)