Audit planning is a continuous
process
True
False​

Answers

Answered by yashkaur8772
0

Answer:

true

Explanation:

Planning can easily be misconstrued as a discrete phase of an audit, taking place only when scheduled. Instead, it should be viewed as a continuous process that begins upon completion of the prior audit and ends with completion of the current engagement.