Aw the network from the following activities and find the critical path and total duration of the project :
activity
1-2
1-3
2-3
2-4
3-4 (dummy) 3-5
4-6 5-6
duration (weeks)
6 8 4 3 0 6 10 3
8. "
Answers
Answered by
0
Answer:
one by two
second one is 3 by 4
third is 65
Step-by-step explanation:
please please mark as brain list list