28. A and B can do a piece of work in 18 days, B and
C can do in 24 days, A and C in 36 days. The time
taken by them to do this work together is
(a) 16 days
(b) 15 days
(c) 12 days
(d) 8 days
Answers
Answer:
hope it helps you to explain
Step-by-step explanation:
mark as brianliest
Given:
- (A+B) can do a piece of work in 18 days
- (B+C) can do a piece of work in 24 days.
- (A+C) can do a piece of work in 36 days.
To Find :
- How long they will take to complete work together?
Solution:
Here, given that (A+B), (B+C) and (C+A) are doing a work in 18 days, 24days and 36days respectively.
- Let suppose that total work in 1
Therefore,
- (A+B)'s one day work = 1/18
- (B+C)'s one day work = 1/24
- (C+A)'s one day work = 1/36
Now,
We found that (A+B),(B+C) and (C+A) can do 1/18,1/24 and 1/36 work in one day.
Let find that how much work they will do together in one day :-
⟹ (A+B) +(B+C) + (C+A) one day's work =
⟹ 2(A+B+C) one day's work =
⟹ 2(A+B+C) one day's work =
⟹ 2(A+B+C) one day's work =
⟹ (A+B+C) one day's work =
⟹ (A+B+C) one day's work =
Now,
We found that A,B and C together can do 1/16 of total work in 1 day where total work is 1[we have supposed]
Therefore,
⟹ Time taken by (A+B+C) together =
⟹ Time taken by (A+B+C) together = 1×16
⟹ Time taken by (A+B+C) together = 16days[Option 'A']
__________________
LEARN MORE FROM HERE :-
- A and B can finish a work in 15 days from B and C in 20 days and A and C can finish it in 30 days, then in how many ... https://brainly.in/question/39406319?utm_source=android&utm_medium=share&utm_campaign=question
- A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 12 days.In how many days can A, B and C... https://brainly.in/question/39550878?utm_source=android&utm_medium=share&utm_campaign=question