Math, asked by ravikumar444, 3 months ago

Ayush and Rahul together complete a work in half of time of veer,while Ayush and veer together can complete same work in 1/3rd time of Rahul .if they together complete a piece of work in 30days.then in how many days Rahul can alone complete the work.​

Answers

Answered by konkimallakarthik
0

Answer:

22.5 days

Step-by-step explanation:

let time required to do work by rahul is x

by ayush is y

by veer is z

given x+y=z/2

y+z=x/3..²

and x+y+z=30 days

from ²

x+x/3=30

4x/3=30

4x=90

x=90/4

x=22.5

hope my answer helps you

Answered by mathdude500
2

\large\underline{\sf{Solution-}}

Let

  • Time taken by Ayush alone to finish the work be 'x' days.

  • Time taken by Rahul alone to finish the work be 'y' days.

  • Time taken by Veer alone to finish the work be 'z' days.

So,

\rm :\longmapsto\: \: Ayush \:  1 \:  day \: work \:  = \dfrac{1}{x}

\rm :\longmapsto\: \: Rahul \: 1 \: day \: work = \dfrac{1}{y}

\rm :\longmapsto\: \: Veer \: 1 \: day \: work = \dfrac{1}{z}

Now,

According to statement,

  • Ayush and Rahul together complete a work in half of time of veer.

So, there 1 day work is

\rm :\longmapsto\:\dfrac{1}{x}  + \dfrac{1}{y}  = \dfrac{2}{z}  -  -  - (1)

Also, given that

  • Ayush and veer together can complete same work in 1/3rd time of Rahul.

So, there 1 day work is

\rm :\longmapsto\:\dfrac{1}{x}   + \dfrac{1}{z}  = \dfrac{3}{y}  -  -  - (2)

Also, given that

  • They together complete a piece of work in 30days.

So, there 1 day work is

\rm :\longmapsto\:\dfrac{1}{x}  + \dfrac{1}{y}  + \dfrac{1}{z}  = \dfrac{1}{30}

\rm :\longmapsto\:\dfrac{2}{z}  + \dfrac{1}{z}  = \dfrac{1}{30}  \: \:  \:  \:  \:   \:  \{using \: (1) \}

\rm :\longmapsto\:\dfrac{3}{z}  = \dfrac{1}{30}

\bf\implies \:z \:  =  \: 90 -  -  - (4)

Now,

On Subtracting equation (2) from equation (1), we get

\rm :\longmapsto\:\dfrac{1}{y}  - \dfrac{1}{z}  = \dfrac{2}{z}  - \dfrac{3}{y}

\rm :\longmapsto\:\dfrac{4}{y}  = \dfrac{3}{z}

\rm :\longmapsto\:\dfrac{4}{y}  = \dfrac{3}{90}  \:  \:  \:  \:  \:  \:  \:  \{ \because \: z = 90 \}

\rm :\longmapsto\:\dfrac{4}{y} =  \dfrac{1}{30}

\bf\implies \:y = 120

\bf\implies \:Rahul \: alone \: take \: 120 \: days \: to \: finish \: the \: work.

Similar questions