Azhar is 4 times as good a workman as Balaraj and therefore is able to finish a job in 45 days less than Balaraj. Working together, they can do it in:
A) 6 days B) 18 days C) 24 days D) 12 days
Answers
Answered by
0
Answer:
C is the answer mate......