b) 24 men working at 8 hours per day can do piece of work in 15 days. In how many days can
20 men working at 9 hour per day can complete the same work?

Answers

Answered by coldelena
2

24 men working 8 hrs / day can do a piece in 15 days

∴ Total work units =24×8×15

=2880

No.of days required by 20 men, working at

a hrs/day= 2880/(20×9)

=16 days.

Hey there I hope this helped you out ❣️

Please mark me as Brainliest if so.

Answered by yogavamsi1999
0

Step-by-step explanation:

ok.

24 men working 8 hrs / day can do a piece in 15 days

∴ Total work units =24×8×15

=2880

No.of days required by 20 men, working at

a hrs/day=

20×9

2880

16 days