b) A and B can do a piece of work in 8 days. If they work separately , B
would take 12 days more than A. How long A alone can do the work.
Answers
Answered by
2
Answer:
here is your answer
hope it is helpful
Attachments:

Answered by
2
A+B one day work will be 1/8
B one day work will be 1/12
(A+B) - B = A
1/8-1/12
LCM IS 24
3/24 - 2/24
1/24
A takes 24 days