b) A can do a piece of work in 4 days and B can do a piece of work in 6 days. How long will they take to complete it together?​

Answers

Answered by ubeshmd54
0

It is given that

A can do a piece of work in 4 days B can do the same work in 5 days

A's one day's work = 1/4

B's one day's work = 1/5

A and B both one-day work =

4

1

+

5

1

=

20

5+4

=

20

9

A and B two day's work =

20

9

×2=

10

9

Answered by luitelashish3
0

Answer:

2.4 days

Step-by-step explanation:

a can do work one day 1/4

b can do worn in one day 1/6

mix them

both can do work one day 5/12

finish in 1/5/12=12/5

or 2.4 days