(b) From the following information in respect of material number 30, calculate re-order level, minimum level and maximum level of stock of material number30.

Re-order quantity
1,500 units
Re-order period
4-6 weeks
Consumption per week:
Maximum
400 units
Normal
300 units
Minimum
250 units​