B is 200% efficent than A and 50% efficient than C, if all if them work together for 2 days to complete the work, then in how many days a alone can complete the work?
Answers
Answered by
1
let A capacity = x work per day
as B is 200% efficient, (B capacity - A capacity)/A capacity*100 =200
solving the above will give B capacity= 3x
same way (B capacity - C capacity)/C capacity*100 =50
solving above will give C capacity= 2x
so in one day total work done by A, B, C is x+2x+3x=6x
in two days = 12x
so a alone will complete work of 12x in 12x/x = 12 days.