B will do a work in 4 days and M will do the same work in 12 days. in how many days will the two do it together?
Answers
Answered by
2
3 days is the answer....
Attachments:
Lokesh12311:
how do you get 12 in centre
Answered by
1
Total no of days B works=4
Total no of days M works=12
One day work of B=1/4
One day work of M=1/12
Total no of days the will work together=1/4+1/12 ( Take LCM )
=(3+1)/12
=4/12
=1/3
M and B works together=3 days
Total no of days M works=12
One day work of B=1/4
One day work of M=1/12
Total no of days the will work together=1/4+1/12 ( Take LCM )
=(3+1)/12
=4/12
=1/3
M and B works together=3 days