Balancing depth of a canal is achieved when select one:
a. The depth of cutting and height of embankment are equal
b. The discharge in cutting section and between the embankment section are equal
c. The volume of exavated portion and the bank is same
d. The discharge carried by the canal is maximum
Answers
Answered by
0
"a "is the right answer
riyakadam174:
mark as brainliest answer
Answered by
0
❗❗option (a) is the correct answer of your question ❗❗