based on the NASA statistics on budget and schedule overruns vs.time spent on requirements process.what is the recommended amount of time to spend on the requirements stage
Answers
Answered by
4
Answer:
As IT systems become an important competitive element in many industries, technology projects are getting larger, touching more parts of the organization, and posing a risk to the company if something goes wrong. Unfortunately, things often do go wrong. Our research, conducted in collaboration with the University of Oxford, suggests that half of all large IT projects—defined as those with initial price tags exceeding $15 million—massively blow their budgets. On average, large IT projects run 45 percent over budget and 7 percent over time, while delivering 56 percent less value than predicted. Software projects run the highest risk of cost and schedule overruns1 (Exhibit