Math, asked by joisprabhanjan, 1 month ago

be Search SO workers can construct a bridge In 40 days by working & his per day. But they completed 30 days and completed only half of the work. How many more workers are needed to complete the work on time by working 10 hes per day. A 65 B.6O C. 5O D.70​

Answers

Answered by lklalanhzb
0

Step-by-step explanation:

Mandays required to complete the work=1500*60=90000

Men required to complete the work in 40days=90000/40=2250

No of more men required=2250–1500=750 Ans