Math, asked by himanshuvyas947, 2 days ago

Bob and his team consist of 8 members. They can complete the construction of one building in 7 days. They get a contract to construct 4 buildings. However, Bob gets injured after constructing 2 buildings and other members constructed the remaining two buildings. How many days will it take to complete the construction of the 4 buildings?​

Answers

Answered by farhan55647fa
2

Answer:

Any worker day question can be solved with the concept of man-days.

As it takes 3 days for 10 workers to build a house. This implies a house needs 30 man-days to be built up.

Therefore, 4 houses will need 120 man-days.

Now, we have 15 workers.

Hence we would need 8 days (120/15) to build 4 houses.

Answered by SteffiPaul
3

It will take 27 days to complete the construction of the 4 buildings.

Given,

Number of members = 8

Time is taken to complete the construction of 1 building = 7 days

Total number of buildings to be constructed = 4

2 buildings are constructed by 8 members

Rest 2 buildings are constructed by 7 members

To Find,

Total number of days taken to complete the construction of the 4 buildings

Solution,

For the initial 2 buildings, 8 members will complete the construction in 7 x 2 = 14 days. (By unitary method)

Then, we have the formula,

M1W1/D1 = M2W2/D2

M is the total number of people who worked for work W in D days.

(8 x 2)/14 = (7 x 2)/D2

We have put the values accordingly as case 1 and case 2.

16/14 = 14/D2

D2=14x14/16 days

D2=196/16 days

D2 ≅ 13 days

Hence, it took around 13 days for 7 members to complete the construction of the rest of 2 buildings.

So, total number of days for the construction of 4 buildings = 14 + 13 = 27 days. This is the final answer.

#SPJ2