both take to do it, working together?
7 A and B, working together can finish a piece of work in 6 days, while A alone can
9 days. How much time will B alone take to finish it?
Answers
Answered by
1
Answer:
18 days
Step-by-step explanation:
A's one day work = 1/9
A + B one day work = 1/6
Therefore 1/9 + B one day work-1/6 B one day work = 1 / 6-1 / 9 = 1/18
Therfore B alone canfinish the work in 18 days.