Math, asked by rekha1304198039, 8 months ago

(c) 15 days
4. A alone can complete a work in 18 days
and B alone in 15 days. B alone worked at
it for 10 days and then left the work. In
how many more days, will A alone
complete the remaining work?
(a) 5
(b) 5
2
(d)
(c) 6
2​

Answers

Answered by rachealadeoye12
1

Answer:

(a) 5

Step-by-step explanation: