English, asked by ervikas9829, 6 months ago

© How many bags of Cement required in
125m3 brick Masonry work?​

Answers

Answered by Anonymous
1

Answer:

How many cement bags are required for 1 cubic metre brick work?

Your newborn may be vulnerable to these 6 serious diseases.

Thanks for the question.

1 m3 brick work contains bricks as well as mortar.

Considering standard brick size of 225 x 112.5 x 75 mm.

So, volume of each brick = 0.225*0.1125*0.075 = 0.00189 m3.

Now, considering 10 mm mortar on each side of brick, then volume of one brick with mortar will be = 0.235*0.1225*0.085 = 0.00244 m3.

So, if total volume 1 m3, number of bricks required = 1/0.00244 = 409.83 = 410 (say).

So, the volume of mortar = (0.00244 - 0.00189)*410 = 0.2255 m3.

Now, if we consider 1:4 ratio of mortar then,

Cement required, = 0.2255*1 /5 = 0.0451 m3.

We know, the volume of 1 bag cement = 0.035 m3.

So, the number of bags required, = 0.0451/0.035 = 1.28 bags.

I hope it will be helpful to you friend

Similar questions