C] Six workers take 18 days to weed a field. How many days would 9 workers take? How many
would 10 take?
Ans:- [Solution]
Answers
Answered by
0
Answer:
12 is your answer
I hope it will help you
Attachments:
Answered by
0
Step-by-step explanation: 1 worker will take 18*6 days
= 108days
9 workers will take
= 108/9
= 12 days
10 workers will take
108/10
= 10.8 days