C. the shortest time to complete a network is equal to the duration of the longest path through the network
Answers
Answered by
7
AON and AOA networks can both be used to depict any project network.The shortest time to complete a network is equal to the duration of the longest path through the network.
the shortest time to complete a network is equal to the duration of the longest path through the network.
the shortest time to complete a network is equal to the duration of the longest path through the network.