Calculate cash received given the following details : Materials = Rs. 20000, Work Certified = Rs. 1600000, Work uncertified = Rs. 200000, Retention Rate = 20%
Answers
Answered by
0
Answer:
Explanation:
The work which has not completed but not certified is work uncertified. work certified and uncertified work will consider as credit side of the contracter account .
work certified + uncertified = 1600000 + 200000
= 1800000
Retention rate = 20 %
cash received =1800000 - (1800000 × 20 /100)
= 1800000 - 360000
= 1440000.