Calculate labour Cost Variance:
Standard for 10 units - 5 Hours:
Standard Rate per unit Rs. 15; Actual
Production - 160,000 units; Actual
hours worked - 85,000 hours: Actual
rate per hour Rs. 29.80​

Answers

Answered by stelladsouza2573417
0

Answer:

232000..25458 eykwiavsgwb

Answered by yogeshsahil342
1

Answer:

Std [10 Unit]  Actual [1,60,000 Units]

Hrs Price Amt (₹)  Hrs Price Amt (₹)

5 ₹ 30 150 (10 U x ₹ 15)  85,000 ₹ 29.80 25,33,000

(₹150/5hrs)    

Rev. Std [1,60,000 Units]

 Qty  Price Amt (₹)

80,000  

For 10 Unit    –  5 hrs

For 1,60,000 U  –  ?   ₹ 30 24,00,000

   

a. Labour Cost Variance :

Rev. Std. Cost – Actual Cost

₹ 24,00,000 – ₹ 25,33,000 = ₹ 1,33,000 (Adv)