Calculate the machine hour rate:
Cost of Machine –Rs.12000; Estimated scrap value:Rs.3000
Power of consumption per hour -5units @Rs.0.06 per unit.
Total Repair and Maintenance Charges -Rs.1125:
Standing Charges per year (1800hours) as follows:
1. Rent(1/5th area is occupied) Rs.780
2. Lighting (out of 12points, 2 are used for machine) Rs.288
3. Insurance – Rs.96 and
4. Wage (1/4th for machine) Rs.6000
Answers
Answered by
1
Answer:
machine hour rate= standing charges + flactuation charges
=2.573+5.925
= 8.498
Explanation:
in standing charges
rent = 156; lighting=2880;insurance=96;wage=1500
in flactuation charges
for dep = 12000-3000=9000/1800=5
power=0.3;total repairs=1125/1800=0.625
actually i have confusion in the lighting charges so plz take a view on that but rest is correct as per my knowledge.