Calculate the prime cost from the following information Direct material purchased Rs 1,00,000 Direct material consumed Rs 90,000 Direct labour Rs. 60,000 Direct expenses. Rs. 20,000 Manufacturing overheads Rs. 30,000
Answers
Answered by
7
Answer:
Prime cost = Raw material consumed + Direct labour + Direct expenses = 90000 + 60000 + 20000 = Rs. 170000.