Calculate the prime cost from the following information Direct material purchased Rs 1,00,000 Direct material consumed Rs 90,000 Direct labour Rs. 60,000 Direct expenses. Rs. 20,000 Manufacturing overheads Rs. 30,000 ​

Answers

Answered by tallasindhu8
7

Answer:

Prime cost = Raw material consumed + Direct labour + Direct expenses = 90000 + 60000 + 20000 = Rs. 170000.