Calculate the standard production per shift of 8 hours duration, with the following data. Observed time per unit – 5 minutes. Rating factor – 120%. relation 33.33% of normal time.
Answers
Answered by
5
Explanation:
Observed time per unit – 5 minutes.… ... per shift of 8 hours duration, with the following data. ... Total allowances – 33 1/3% of normal time.
Answered by
0
your answer is 1/3 ,of normal times.