Math, asked by P2avchallajana, 1 year ago

Calculate the Total Number of Men
If 20 persons complete one third of work in 20 days. How many more men should be employed to finish the rest of work in 25 more days?

Answers

Answered by Aadi1111
0
57 is thethe correct answer.