Calculate the Total Time Taken to Complete the Work
A and B can do a piece of work in 12 days, where B and C do it in 15 days and A & C in 20 days. In what time can they do it all working together?

Answers

Answered by rohith9
0
they can complete their work in 45 day s
Answered by NabiDhakal
0
(A+B)+(A+C)+(B+C ) 's work in 1 day
2(A+B+C)=(1/12+1/20+1/15)
2 (A+B+C)=12/60
(A+B+C)=1/5*1/2=1/10 part of work in a day
Thus they do the same work in 10 days