Mass of cement bag (m) = 50 kg
Vertical height (h) = 4 m
Gravitational Force (g) = 10 m/s²
=========================
We have formula for Work done :-
W = (50)(4)(10)
W = (50)(40)
W = 2000
•°• Work done is 2000 J