Math, asked by meghamalar190, 4 months ago

can 20
men working at 9 hours per day do the same work?
3150 m long in 36 days. How
24 men working at 8 hours per day can do a piece of work in 15 days. In how me​

Answers

Answered by Sriramgangster
2

Answer:

16 \: days