Math, asked by saumyaofficial0705, 19 days ago

can anyone solve this pls?

If 6 people working 5 hours a day can complete a piece of work in 15 days how many days will 10 people working 7 hours a day take to complete the same task​

Answers

Answered by Imcomin4u
0

Answer: 125/7 days

Step-by-step explanation:

Let x days be the number of days needed to complete the same task.

5×15÷6=7x÷10

750 = 42x

x = 125/7

And by the way, the task is already completed, so there is no need for the 10 people to build it

Answered by vrindhu2014
0

Answer:

Answer is 125/7 . To know more mark me as  brainliest .

Step-by-step explanation:

Similar questions