Math, asked by HolazoeyAhnaf, 4 months ago

can somebody please help me with this sum​

Attachments:

Answers

Answered by makkenajoshita
1

Answer:

11 hrs 40 min

Step-by-step explanation:

Time taken by 14 men = 6h 40 min =400min

Time taken by 1 man = 400*14

                                   = 5600 min

Time taken by 8 men = 5600/8

                                    = 700 min

                                    =  11 hrs 40 min

                                       