can somebody please help me with this sum
Attachments:
Answers
Answered by
1
Answer:
11 hrs 40 min
Step-by-step explanation:
Time taken by 14 men = 6h 40 min =400min
Time taken by 1 man = 400*14
= 5600 min
Time taken by 8 men = 5600/8
= 700 min
= 11 hrs 40 min