charu and nirmal work complete in 15,10 days.they are working both after some days charu was gone,remaining work nirmal completed in 5 days.charu how many days worked.
Answers
Answered by
2
Hey mate !!
Here's your answer !!
Let us first consider the amount of work done by both in a single day:
Charu = 15 days
Hence in 1 day he has completed 1/15 th of work.
Nirmal = 10 days
Hence in one day he has completed 1/10 th of work.
So if they both work together they complete the work in x days
So amount of work done in a single day = 1/x th of work
=>
Taking LCM we get,
= [tex] \frac{15+10}{15*10} = \frac{1}{x} [/tex]
=
=
=> x = 6 days
So total number of days = 6 days
Hope it helps !!
Cheers !!
Here's your answer !!
Let us first consider the amount of work done by both in a single day:
Charu = 15 days
Hence in 1 day he has completed 1/15 th of work.
Nirmal = 10 days
Hence in one day he has completed 1/10 th of work.
So if they both work together they complete the work in x days
So amount of work done in a single day = 1/x th of work
=>
Taking LCM we get,
= [tex] \frac{15+10}{15*10} = \frac{1}{x} [/tex]
=
=
=> x = 6 days
So total number of days = 6 days
Hope it helps !!
Cheers !!
Answered by
0
Given:
Charu completes in 15 days and Nirmal completes in 10 days
After Charu left, Nirmal completed it in 5 days
To find:
Calculate the number of days to complete the work
Solution:
Let us consider the total amount of “work done” by both in a single day:
Charu = 15 days
So in 1 day, he completed of the work.
Nirmal = 10 days
So in 1 day, he completed of the work.
If both work together, then they complete the work in x days
Then the “total amount of work” done in a single day of the work
Taking LCM we get,
Therefore x = 6 days
Similar questions