Math, asked by patelsalman1107, 19 days ago

Choose the correct sequencing of purchase procedure i preparation of purchase order ii selection of supplier iii receipt of purchase requisition iv return of rejected material 1, 3, 4,2 3, 2, 1,4 2, 4, 3,1 3, 2, 4,1​

Answers

Answered by panushka147
2

Answer:

3,2,1,4

Step-by-step explanation:

c. receipt of purchase requisition. b. selection of supplier. a. preparation of purchase order. d. return of rejected material.