COCOMO-II estimation model is based on
a) Algorithm approach
b) Complex approach
c) Bottom up approach
d) Top down approach
Answers
Answered by
4
Answer:
algorithm approach is the answer in my sight
Answered by
0
COCOMO-II estimation model is based on (a) Algorithm approach
Explanation:
- COCOMO-II was designed and developed in University of Southern California by Barry Boehm in 1997 as a successor of the earlier Constructive Cost Model (COCOMO).
- It is based on the algorithm approach and is designed is to give better and enhanced support to the new software development.
- COCOMO was itself a very good performing model but the only reason for upgrading it into COCOMO-II was that the former didn't go well with the modern software development.