company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item: Machine time Craftsman timeItem X 13 20 Y 19 29The company has 40 hours of machine time available in the next working week but only 35 hours of craftsman time. Machine time is costed at £10 per hour worked and craftsman time is costed at £2 per hour worked. Both machine and craftsman idle times incur no costs. The revenue received for each item produced (all production is sold) is £20 for X and £30 for Y. The company has a specific contract to produce 10 items of X per week for a particular customer.• Formulate the problem of deciding how much to produce per week as a linear program.
Answers
SOLUTION
TO DETERMINE
Formulate the problem of deciding how much to produce per week as a linear program.
EVALUATION
Let number of item X = x
Number of item Y = y
The company has a specific contract to produce 10 items of X per week for a particular customer
Work time for machine
Work time for Craftsman
Let z be the profit
Then
z = ( 20x + 30y ) - 10 × Work time for machine - 2 × Work time for Craftsman
Thus converting the given problem into linear programming problem we get
Subject to :
━━━━━━━━━━━━━━━━
Learn more from Brainly :-
1. A Factory Manufactures Two Products A And B. To Manufacture One Unit Of A, 1.5 Machine Hours And 2.5 Labour Hours Are Re...
https://brainly.in/question/35231883
2. in transportation models designed in linear programming, points of demand is classified as
https://brainly.in/question/34325303