Math, asked by khadeeja3851, 3 months ago

company is involved in the production of two items (X and Y). The resources need to produce X and Y are twofold, namely machine time for automatic processing and craftsman time for hand finishing. The table below gives the number of minutes required for each item: Machine time Craftsman timeItem X 13 20 Y 19 29The company has 40 hours of machine time available in the next working week but only 35 hours of craftsman time. Machine time is costed at £10 per hour worked and craftsman time is costed at £2 per hour worked. Both machine and craftsman idle times incur no costs. The revenue received for each item produced (all production is sold) is £20 for X and £30 for Y. The company has a specific contract to produce 10 items of X per week for a particular customer.• Formulate the problem of deciding how much to produce per week as a linear program.​

Answers

Answered by pulakmath007
9

SOLUTION

TO DETERMINE

Formulate the problem of deciding how much to produce per week as a linear program.

EVALUATION

Let number of item X = x

Number of item Y = y

The company has a specific contract to produce 10 items of X per week for a particular customer

\displaystyle\sf{  \therefore \: x  \geqslant  10} \:  \:  \:  -  -  - (1)

Work time for machine

\displaystyle\sf{ =  (13x + 19y)  \:  \: minutes}

\displaystyle\sf{ =  \frac{13x + 19y}{60}   \:  \: hours}

\displaystyle\sf{  \therefore \:  \:   \frac{13x + 19y}{60}  \leqslant 40}

\displaystyle\sf{  \implies \:  \:   13x + 19y  \leqslant 2400 \:  \:  -  -  - (2)}

Work time for Craftsman

\displaystyle\sf{ =  (20x + 29y) \:  \: minutes}

\displaystyle\sf{ =  \frac{20x + 29y}{60}   \:  \: hours}

\displaystyle\sf{  \therefore \:  \:   \frac{20x + 29y}{60}  \leqslant 35}

\displaystyle\sf{  \implies \:  \:   20x + 29y \leqslant 2100} \:  \:  \:  -  -  - (3)

Let z be the profit

Then

z = ( 20x + 30y ) - 10 × Work time for machine - 2 × Work time for Craftsman

\displaystyle\sf{  \therefore \:  z =(20x + 30y) - 10 \times  \frac{13x + 19y}{60} - 2 \times   \frac{20x + 29y}{60}}

\displaystyle\sf{  \therefore \:  z  =  \frac{1030x + 1552y}{60} }

Thus converting the given problem into linear programming problem we get

\displaystyle\sf{ Maximize \:  \:  z  =  \frac{1030x + 1552y}{60} }

Subject to :

\displaystyle\sf{  \: x  \geqslant  10} \:  \:  \:

\displaystyle\sf{  \:   13x + 19y  \leqslant 2400 \:  \: }

\displaystyle\sf{   \:   20x + 29y \leqslant 2100} \:  \:  \:

 \sf{With \:  \: x \geqslant 0 \:  \: and \:  \: y \geqslant 0}

━━━━━━━━━━━━━━━━

Learn more from Brainly :-

1. A Factory Manufactures Two Products A And B. To Manufacture One Unit Of A, 1.5 Machine Hours And 2.5 Labour Hours Are Re...

https://brainly.in/question/35231883

2. in transportation models designed in linear programming, points of demand is classified as

https://brainly.in/question/34325303

Similar questions