Business Studies, asked by mohduwais123, 3 months ago

Company XYZ uses EDD priority rule for sequencing its jobs. Consider the following
scheduling data for the company:
Job Processing time Due Date
A
3
В
4
2
7
D
6
9
E
1
2
NOVOU
a) E-A-C-D-B
b) E-C-A-B-D
c) E-A-B-C-D
d) A-B-D-E-C

Answers

Answered by meharjanjua8gmailcom
0

Answer:

answer a is the correct one