Company XYZ uses EDD priority rule for sequencing its jobs. Consider the following
scheduling data for the company:
Job| Processingtime |DueDate
A. 3 5
B. 4 6
C. 2 7
D. 6 9
E. 1 2

a) E-A-C-D-B
b) E-C-A-B-D
c) E-A-B-C-D
d) A-B-D-E-C​

Answers

Answered by divekarsankalp988
0

B 4 6

is the right answer dear friend