Accountancy, asked by Avinav4125, 1 year ago

Compute the multifactor productivity measure for an eight-hour day in which the usable output was 300 units, produced by three workers who used 600 pounds of materials. Workers have an hourly wage of $20, and material cost is $1 per pound. Overhead is 1.5 times labor cost.

Answers

Answered by itsTIGER
22

Compute the multifactor productivity measure for an. ... materials. Workers have an hourly wage of $20, and material cost is $1 per pound. Overhead is 1.5 times labor cost. Labor cost ...

Answered by HrishikeshSangha
9

The answer is \frac{1}{6}.

Given:

Eight hour day

Usable output is 300 units

Weight of materials output = 600 pounds

Hourly wage of 3 workers each = 20

Overhead cost is 1.5 times the labour cost

To Find:

The multifactor productivity measure

Solution:

The total labour cost is 3*8*20=480

Hence the overhead cost is 1.5*480=720

The materials cost is 600*1=600

The multifactor productivity measure is given by

\frac {Out put}{materials+labour+overhead} = \frac{300}{480+720+600} =\frac{1}{6}

The multifactor productivity measure is \frac{1}{6}.