Accountancy, asked by Lauren111, 10 months ago

Contract completed is 3\4.Work certified is 1\2 of contract price.Cost of 3\4 work is 3,00, 000.Calculate the cost of work uncertified.

Answers

Answered by sonalip1219
11

The cost of work uncertified is 200,000

Explanation:

Computing the cost of work done in 1 as:

Value of 3/4 work completed = 300,000

For 1

Value of 1 work completed = 300,000 × 4/ 3

Value of 1 work completed = 100,000 × 4

Value of 1 work completed = 400,000

So, 1/2 work is certified as computed as:

Value of work certified = 400,000 × 1/2

Value of work certified = 200,000

Now, computing the cost of work uncertified as the formula:

Income on a Contract = Value of Work Certified + Cost of Work Uncertified

So,

Cost of work uncertified = Income on a contract - Value of work certified

where

Income on a contract is 400,000

Value of work certified is 200,000

putting the valued above:

Cost of work uncertified = 400,000 - 200,000

Cost of work uncertified = 200,000