Contract completed is 3\4.Work certified is 1\2 of contract price.Cost of 3\4 work is 3,00, 000.Calculate the cost of work uncertified.
Answers
Answered by
11
The cost of work uncertified is 200,000
Explanation:
Computing the cost of work done in 1 as:
Value of 3/4 work completed = 300,000
For 1
Value of 1 work completed = 300,000 × 4/ 3
Value of 1 work completed = 100,000 × 4
Value of 1 work completed = 400,000
So, 1/2 work is certified as computed as:
Value of work certified = 400,000 × 1/2
Value of work certified = 200,000
Now, computing the cost of work uncertified as the formula:
Income on a Contract = Value of Work Certified + Cost of Work Uncertified
So,
Cost of work uncertified = Income on a contract - Value of work certified
where
Income on a contract is 400,000
Value of work certified is 200,000
putting the valued above:
Cost of work uncertified = 400,000 - 200,000
Cost of work uncertified = 200,000