contract of construction of job specifies penalty for delay of completion beyond a certain date as follow Rs.200 for first day ,Rs.250 for second day,Rs.300 for 3rd day etc

1. how much money the contractor has to pay as penalty, if he has delayed
work by 20 days
2. which mathematical concept is used in the above problem
3. which value should be promoted in this problem​

Answers

Answered by banerjeesubhojit92
1

Answer:

Please follow me

Step-by-step explanation:

a contract of construction job specifies a penalty for delay of completion beyond a certain date as follows: rs200 for first day rs 250 for second day and third day rs300etc the penalty for each succeeding day being rs 50 more than preceeding day

please follow me

Answered by usharanisimhadri1987
1

Answer:

ans:1. Rs.1200

ans:2. Arithmetic progression

ans:3. Rs.50