contractor has to finisha work in20 days and employees30men on the job if the work is to be finished in 15 days,the number of extra men to be employed is
Answers
Answered by
2
more men, less days
It is in inverse variation
let the no. of extra men be x
ab=k
15*x=20*30
15x=600
x=600/15
40men
hope it helps
please mark as brainlist