cost.
Ans. [Raw Materials Consumed * 4,55,000; Prime Cost: 5,51,000; Work Cost * 5,99,000;
Cost of Production 7,18,800].
5. Following information for 2019 is given :
₹
₹
Materials
2,00,000 Factory Expenses
2,40,000
Direct Labour
1,60,000 Office and Administrative Overheads 1,20,000
Ascertain the cost of a job which is likely to require materials of the value of * 10,000 and
wages to the extent of 1 6,000.
(C.H.S.E. Odisha)
Ans. [30,000]