Cycle Trends is introducing two new lightweight bicycle frames, the Deluxe and the Professional, to be made
from aluminum and steel alloys. The anticipated unit profits are $10 for the Deluxe and $15 for the
Professional. The number of pounds of each alloy needed per frame is given in a table below. A
supplier delivers 100 pounds of the aluminum alloy and 80 pounds of the steel alloy weekly. How many
Deluxe and Professional frames should Cycle Trends produce each week?
Pounds of alloy needed per frame
Aluminum Alloy Steel Alloy
Deluxe 2
3
Professional 4
2
Formulate and solve this Linear Programming problem.​