Accountancy, asked by keshu5854, 2 months ago

d) Fixed Overhead Cost Variance is the difference between​

Answers

Answered by 1157684
6

Answer:

The fixed overhead spending variance is the difference between actual and budgeted fixed overhead costs. The fixed overhead production volume variance is the difference between budgeted and applied fixed overhead costs.