d) Fixed Overhead Cost Variance is the difference between:
i) Actual fixed cost and budgeted fixed cost.
ii) Actual fixed cost and standard fixed cost
iii) Actual Fixed cost and Applied fixed cost
iv) Budgeted fixed cost and Applied fixed cost.
Answers
Answered by
1
Answer:
d) Fixed Overhead Cost Variance is the difference between:
i) Actual fixed cost and budgeted fixed cost.
ii) Actual fixed cost and standard fixed cost
iii) Actual Fixed cost and Applied fixed cost
iv) Budgeted fixed cost and Applied fixed cost.