7 men can complete a piece of work in 12
days. How many additional men will be
required to complete double the work in 8
days?
(A) 28
(B) 21
(C) 14
(D) 7
HICHEST QL​

Answers

Answered by digvijay49
1

Answer:

Hope you like this answer❣️

Step-by-step explanation:

Correct Answer:

C) 14

Description for Correct answer:

7men×12days1work=(7+n)men×8days2work7men×12days1work=(7+n)men×8days2work

(n is additional no. of men required)

21=7+n21=7+n

n=14 men