D.U.
A and B together can do a piece of work in 30 days. A having worked for 16 days,
B finishes the remaining work alone in 44 days. In how many days shall B finish the
whole work alone ?
(C.B.I. 1997)
Answers
Answered by
0
Answer:
Hello,
Please find the method below.
Let A's 1 day's work = x and B's 1 day's work = y.
Both A's and B's 1 day work=1/30
i.e (A's 1 day + B's 1 day)=1/30
i.e x + y = 1/30........eq1
now,
A having worked for 16 days, B finishes the remaining work alone in 44 days
i.e work done by A in 16 days = 16x
Remaining work done B= 1 - 16x
but Remaining work is done by B in 44days i.e 44y
i.e. 44y=1-16x
i.e 16x+44y=1........eq2
solving eq1 & eq2,
we get,x = 1/60 and y = 1/60
B's 1 day's work = 1/60.
Hence, B alone shall finish the whole work in 60 days