Math, asked by kamalabohara234, 2 months ago

DATE
20 men can complete a work in 36 days.
How many men should be
added to complete the same work
in 15 days?​

Answers

Answered by hivrajkavre1955
0

Answer:

25 men's 1 day work = 1/36

1 man's 1 day work = [1/(36 x 25)]

So, 15 men's 1 day work = [1/(36x 25)] x 15 = 1/60.

So, it will take 60 days for 15 men to complete the work.