DATE
EXERCISE 9.1
1. An employer has a workforce of 300
employees to finish a project in 8 months.
How many extra employees should he
employ to complete the project in 6
months?
Answers
Answered by
0
Step-by-step explanation:
100 extra employees we should want
Similar questions
Math,
2 months ago
Math,
2 months ago
Social Sciences,
2 months ago
Social Sciences,
4 months ago
Math,
4 months ago
Math,
9 months ago
Environmental Sciences,
9 months ago